US 89 Shoulders Project Update 27

Sunday, September 24, 2017 - 1:45pm
UDOT

US 89 Shoulders Project - September 21, 2017

 

Current Work

▪ Crews have completed shoulder paving between Blazer Plastics and 8200 South.
▪ Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.

▪

Crews have completed shoulder paving between Blazer Plastics and 8200 South.

▪

Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.

▪

Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.

Current Closures

▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

▪

The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

 

Upcoming Work

▪ Once paving is complete road paint and signs will be placed.
▪ Work in front of Pettingills is expected to begin in a few weeks.

▪

Once paving is complete road paint and signs will be placed.

▪

Work in front of Pettingills is expected to begin in a few weeks.

 

Project Location

UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.

Purpose of the Project

This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.

What to Expect

▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete the end of October 2017.

▪

Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.

▪

Anticipate construction noise and vibrations.

▪

The right travel lane will be closed in the areas in which crews are working.

▪

This project is expected to be complete the end of October 2017.

 